Raj Kumar Johri v. State of M.P., (SC) BS5021
SUPREME COURT OF INDIA

Before:- V.N. Khare, Ashok Bhan and D.M. Dharmadhikari, JJ.

Civil Appeal Nos. 5938-5939 of 2000. D/d. 7.3.2002.

Raj Kumar Johri - Appellants

Versus

State of M.P. - Respondents

For the Appearing Parties :- S.S. Ray and U.N. Bachawat, Sr. Advs., Sushil Kumar Jain, A.P. Dhamija, Ms. Anjali Doshi, Ms. Ruchi Kohli, Adv. for B.K. Satija, B.S. Banthia, Ms. Vibha Datta Makhija, Ms. Bharti Tyagi, S.K. Agnihotri, Advocates.

Land Acquisition Act, 1894, Sections 4 and 6 - Delay in completion of acquisition proceedings - Deemed date given by the court to the notification to enable the landowners to have more compensation - Cannot be stretched by the landowners so as to challenge the proceedings on the ground of delay in completion.

[Para 12]

Cases Referred :-

Ujjain Vikas Pradhikaran v. Raj Kumar Johri & Ors., 1992(1) SCC 328.

Macheri Puthusseri Ahmed v. Kuthir Avattam Estate Receiver, 1996(6) SCC 185.

Supreme Court Bar Association v. Union of India, 1998(4) SCC 409.

ORDER

V.N. Khare, J. - In September, 1977 for acquisition of more than 600 hectares of land, a notification under Section 4(1) of the Land Acquisition Act (for short "the Act') was issued for the purpose of development of Ujjain, a historical town in Madhya Pradesh. On September 17, 1980, for different reasons the notification was quashed. On 21st August, 1985 the impugned notification was issued afresh under Section 4(1) of the Act. Declaration under Section 6 was issued on 25th of July, 1986. The award was made on 22nd July, 1988.

2. The appellants whose land had been acquired filed Writ Petition No. 1707 of 1986 challenging the notification under section 4 and the declaration under section 6 of the Act to the extent of the acquisition of their land. Indore Bench of the High Court rendered the judgment annulling the notification issued under section 4 of the Act by the holding that Scheme No. 23 framed under M.P. Nagar Tatha Gram Nivesh Adhiniyam, 1973 did not operate against certain specified land of the respondent Ujjains Vikas Pradhikaran (hereinafter referred to as the "Development Authority').

3. The Development Authority, being aggrieved, against the judgment of the High Court filed Civil Appeal Nos. 4554-4556 of 1991 which were disposed of by an order of this Court on November 14, 1991. The same is reported in Ujjain Vikas Pradhikaran v. Raj Kumar Johri & Ors., 1992(1) SCC 328.

4. Although a finding was recorded by this Court that the judgment of the High Court could not be faulted with, but still it was held that due to the peculiar facts and circumstances of the judgment of the High Court could not be sustained, accordingly, the judgment of the High Court was set aside and the acquisition of the land was upheld.

5. Keeping in view the peculiar facts and circumstances of the case, the date of notification under section 4(1) was postponed to 1st January, 1988 for the purpose of determination of the compensation. It was observed :

6. A perusal of this order would show that a deemed date to the notification under Section 4(1) of the Act was given for the purpose of giving enhanced compensation to the claimants in the appeal and the notification under Section 6 was kept intact. It was made clear that the other claimants whose land may have been acquired under the same notification would not be entitled to get enhanced compensation under Section 28A of the Act because of the deemed date of Notification under Section 4(1) given to the appellants.

7. The appellants thereafter filed Writ Petition No. 1931 of 1993 in the High Court challenging the acquisition proceedings, inter alia, on the ground that subsequent to the order passed by this Court, no notification under Section 6 or an award under Section 11 were made, thereby rendering the acquisition proceedings non-est. The High Court rejected the writ petition holding that decision on these points would amount to reviewing the order of this Court. The appellants were advised to approach the Supreme Court for clarification or modification of the order passed by it.

Thereafter the claimants filed these appeals. The Development Authority has also filed the cross appeal.

8. Shri Sidharth Shankar Ray, learned senior Advocate appearing for the appellants contended that keeping in view the scheme of the Act, the authorities were required to issue a fresh declaration under Section 6 of the Act within one year of the deemed date of notification under Section 4(1) and an award within two years from the date of declaration under section 6. And if the declaration under Section 6 is taken from the date of rendering of judgment by this Court, i.e., 14th November, 1991 then failure to make the award within two years from that date resulted in the lapsing of the entire acquisition proceedings.

9. We do not find any force in this submission. The earlier judgment of this Court can be divided into two parts. In the first part this Court set aside the order of the High Court and upheld the acquisition proceedings. In the second portion in order to give more compensation to the owners of land a deemed date was given to the notification under section 4(1). The deemed date to the notification under section 4 was given for the benefit of the appellants only and not to any other land owners whose land were acquired. This Court took care to mention that although the price of the land had increased tremendously owing to the improvements made by the development authority after issuance of notification under Section 4 but the appellants would be entitled to only 25% of the potential value of the land relatable to the improvements made by the development authority. The Court after giving a deemed date of notification did not say that from the deemed date given to notification under section 4, procedure envisaged under the Act of making the declaration under Section 6 or an award under Section 11/11-A was to be followed. Rather the Court gave liberty to the development authority to take possession of the land in accordance with law. Possession could be taken by the authority under Section 16. Fresh declaration under section 6 was not required to be issued. An award in terms of the section 11/11A of the Act was also not required to be given within two years, as has been contended by the learned senior counsel for the appellants. The direction given by the Court was for redetermination of the compensation only. The amount of compensation was to redetermined keeping in view the deemed date given to the notification under section 4 and the improvements made by the authorities between 2nd August, 1985 (the original date of issuance of notification) and the 1st January, 1988 (the deemed date of notification). The appellants' entitlement to the increase in the potential value of the land was limited to 25% only. The development authority was held entitled to take possession of the land under section 16 subject to redetermination of the amount of compensation and not subject to the giving of an award in terms of section 11/11A.

10. This Court in Macheri Puthusseri Ahmed v. Kuthir Avattam Estate Receiver, 1996(6) SCC 185 has held that whenever a deemed date is given by creating a legal fiction then the Court is required to ascertain for what purpose the fiction is created and after ascertaining this, the Court is to assume all those facts and consequences which are incidental or inevitable corollaries to give effect to the fiction. While construing the fiction it is not open to the Court to extend the same beyond the purpose for which it was created. It cannot also be extended by importing another fiction. The deemed date to the notification under section 4 was given by creating a legal fiction for giving enhanced compensation and it has to be limited to that only. It cannot be extended beyond it leading to the issuance of fresh declaration under section 6 or giving a fresh award under Section 11.

11. Due to the pendency of the writ petition in the High Court and due to the fact that the proceedings were adjourned before the Land Acquisition Officer nearly 40 times the amount of compensation could not be redetermined at an early date. It was redetermined on 1st January, 1998 and the possession was taken by the authorities on 9th March, 1998.

12. Shri Ray then argued that the earlier judgment rendered by this Court being against the statutory provisions would be deemed to be an non est judgment and therefore not binding on the parties. That if it be deemed that this Court decided the earlier case in exercise of its extra-ordinary power under Article 142 of the Constitution even then it is bad in law because the Court cannot exercise its power under Article 142 in the face of express statutory provisions. That the appellants could not be deprived of their property without giving market price for the same. For this he made reference to a number of judgments including the judgment of the Constitution Bench in Supreme Court Bar Association v. Union of India & Anr., 1998(4) SCC 409. In particular reference was made to paras 47, 48, 50, 51, 52, 55 and 56 of the said judgment. The submission has no force. In the earlier judgment the Court had upheld the acquisition proceedings but in order to give more compensation to the landowners in that case a deemed date was given to the notification under Section 4. So far as the upholding of the acquisition proceedings is concerned it cannot be held that it is against any statutory provision. That part of the judgment cannot be touched. In any case it is too late to challenge the upholding of the acquisition proceedings in an appeal before a bench of co-ordinate jurisdiction. The other part is of giving deemed date to the notification under section 4 and limiting the benefits arising therefrom. The same is for the benefit of the claimants-appellants. It would not be in the interest of the appellants to get it set aside. Nor would we like to do it.

13. For the reasons stated above, we do not find any merit in the appeals filed by the claimants and dismiss the same. The cross appeal filed by the development authority lacks merit and is also dismissed.

14. Counsel for the appellants then contended that the claimants have not been given any compensation till date. If that be so, the development authority is directed to pay the compensation to the claimants within one month of the date of receipt/production of a certified copy of this order.

15. It was brought to our notice that the claimants have already filed a reference petition under Section 18 of the Act for claiming enhanced compensation. If that be so, the reference petition be decided in accordance with law keeping in view the directions given by this Court in the earlier judgment dated 14th November, 1991. There will be no order as to costs.

All the I.A.'s are disposed of as infructuous.

Appeals dismissed.